All utilities › Idaho › Rocky Mountain Power
Rocky Mountain Power (PacifiCorp) - Idaho: what it publishes for small generators (qualifying facilities) under PURPA, field by field, with the source for each. Checked on October 4, 2026.
When this may change: Annual SAR natural-gas update: per Orders 37109/37110/37111 future update cases are initiated within one month of EIA's Annual Energy Outlook publication, effective three months after publication (Avista/PacifiCorp orders say 'within three months'). Rates are also re-run when a utility's cost of capital changes in a general rate case.
Rates, eligibility and contract terms change: confirm them with the utility or the state utility commission before relying on them.
| Schedule | No standard-offer rate schedule found in RMP's Idaho tariff; standard offer is the IPUC-published SAR avoided cost rates for PacifiCorp ('PacifiCorp Avoided Costs Rates For New Contracts', Order No. 37111). Electric Service Schedule No. 38, Qualifying Facility Avoided Cost Procedures, covers QFs above the published-rate caps. Note: RMP's Idaho tariff index lists only Schedule 38 for QFs. Source: puc.idaho.gov: PacifiCorp Rates Order No. 37111 - New Contract… · also: puc.idaho.gov: 15, rockymountainpower.net: 038_Qualifying_Facility_Avoided_Cost_Procedures… · checked 2026-10-04 | |||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Docket or order | IPUC Case No. PAC-E-26-08, Order No. 37111 (August 3, 2026)Source: puc.idaho.gov: 20260803Final_Order_No_37111.pdf · checked 2026-10-04 | |||||||||||||||
| Effective date | 2026-08-03 Note: Order approves rates 'effective as of the date of this order', dated 3rd day of August 2026. Source: puc.idaho.gov: 20260803Final_Order_No_37111.pdf · checked 2026-10-04 | |||||||||||||||
| Next update | Annual SAR natural-gas update: per Orders 37109/37110/37111 future update cases are initiated within one month of EIA's Annual Energy Outlook publication, effective three months after publication (Avista/PacifiCorp orders say 'within three months'). Rates are also re-run when a utility's cost of capital changes in a general rate case.Source: puc.idaho.gov: 20260803Final_Order_No_37111.pdf · also: puc.idaho.gov: 20251212Final_Order_No_36871.pdf, puc.idaho.gov: 20260728Final_Order_No_37109.pdf, puc.idaho.gov: 20260803Final_Order_No_37110.pdf · checked 2026-10-04 | |||||||||||||||
| Size cap | Wind and solar: 100 kW or smaller; non-wind/non-solar: smaller than 10 aMW. Above-cap QFs use Schedule 38 (IRP-based).Source: puc.idaho.gov: PacifiCorp Rates Order No. 37111 - New Contract… · also: rockymountainpower.net: 038_Qualifying_Facility_Avoided_Cost_Procedures… · checked 2026-10-04 | |||||||||||||||
| Resource types | Published non-fueled tables for Wind, Solar, Non-seasonal hydro, Seasonal hydro, Other.Source: puc.idaho.gov: PacifiCorp Rates Order No. 37111 - New Contract… · checked 2026-10-04 | |||||||||||||||
| Energy rate structure | By resource type, project online year and contract length; levelized or non-levelized flat price, shaped into Heavy/Light Load Hour prices for each month by monthly weighting factors (e.g. Jan HLH 103%/LLH 94%; Dec HLH 129%/LLH 120%). Wind/solar integration charges column shown 'NA'. Rates are published by IPUC per online year (2026-2031) and contract length (1-20 years), levelized and non-levelized; the 'Rate Effective Date' line in the published PDFs is left as the placeholder 'XXXX XX, 2026'.Source: puc.idaho.gov: PacifiCorp Rates Order No. 37111 - New Contract… · checked 2026-10-04 | |||||||||||||||
| Energy rates (sample cells) |
Copied as printed: a few labelled cells, not the full rate matrix. The whole schedule is linked below. Note: Table columns carry no unit label; units from the SAR model workbook header 'LEVELIZED RATES ($/MWH)' (PAC-E-26-08 Attachment C). Source: puc.idaho.gov: PacifiCorp Rates Order No. 37111 - New Contract… · also: lf-puc.idaho.gov: ElectronicFile.aspx?docid=158027&dbid=0 · checked 2026-10-04 | |||||||||||||||
| Capacity payment | None separate: SAR-based published rates bundle the surrogate resource's levelized carrying (capacity) cost with energy cost. Note: Inferred from SAR model components ('LEVEL CARRYING COST ($/MWh)'); no PacifiCorp Idaho tariff text states it. Source: lf-puc.idaho.gov: ElectronicFile.aspx?docid=158027&dbid=0 · checked 2026-10-04 | |||||||||||||||
| Contract terms | Published rates tabulated for contract lengths of 1 to 20 years (full 20-year term available).Source: puc.idaho.gov: PacifiCorp Rates Order No. 37111 - New Contract… · also: lf-puc.idaho.gov: ElectronicFile.aspx?docid=158024&dbid=0 · checked 2026-10-04 | |||||||||||||||
| Price fixity | Levelized and non-levelized published rates are set per contract length at signing; no RMP Idaho tariff sheet states fixed-for-term language (Idaho Power Schedule 73 and Avista Schedule 62 say non-fueled published rates are fixed for the term). Unverified. We could not fully confirm this from a primary document; see the note. Check the source before using it. Note: Could not find PacifiCorp-specific primary text on fixity. Source: puc.idaho.gov: PacifiCorp Rates Order No. 37111 - New Contract… · checked 2026-10-04 | |||||||||||||||
| Schedule link | https://puc.idaho.gov/FileRoom/PublicFiles/electric/PacifiCorp%20Rates%20Order%20No.%2037111%20-%20New%20Contracts.pdf Note: Above-cap procedures: https://www.rockymountainpower.net/content/dam/pcorp/documents/en/rockymountainpower/rates-regulation/idaho/rates/038_Qualifying_Facility_Avoided_Cost_Procedures.pdf Source: puc.idaho.gov: PacifiCorp Rates Order No. 37111 - New Contract… · checked 2026-10-04 |
Values are copied as printed in the source. Where a value draws on more than one document, every source is listed, primary first.
Also in Idaho: Avista, Idaho Power. All 59 utilities. Get every utility as CSV/JSON.